CRITICAL PATH ANALYSIS OF LONG PRECAST CONCRETE WORKBEAM AT WHEAT WORK AT MAKASSAR NEW PORT USING THE PERT METHOD

Authors

  • Rosa Damayanti Departemen Teknik Kelautan, Universitas Hasanuddin
  • Ashury Ashury Departemen Teknik Kelautan, Universitas Hasanuddin

DOI:

https://doi.org/10.62012/sensistek.v5i2.24751

Keywords:

Keywords: Project, Project Scheduling, Critical Path

Abstract

In a construction activity, there are several aspects that require proper management and processingrequired to have accuracy, determination, performance, accuracy, and safety to produce the appropriate endwith expectations. In a project, it is necessary to handle good scheduling management. Because ofTherefore, it needs to be handled with careful and thorough calculations so that no mistakes occur when the project is in progressjust lasts. The duration of a project does not have to add up the total time of the activity,but enough to find the critical path. Scheduling a project is an outcome factor that canprovide information about the schedule plan and progress of the project. In this case, the resource performance iscosts, personnel, equipment and materials, and project duration planning. When working on a project,problems often arise, namely the project implementation time does not match the agreed time. MatterThis will have a negative impact on the company. As a result, when a project is not well planned,Project implementation involves each other throughout a series of activities that will influence each other.

Downloads

Download data is not yet available.

References

Azizah, N. 2017. Penjadwalan Ulang Proyek Pembangunan Gedung Kantor 2 Lantai Menggunakan Metode CPM dan PERT di PT. Sumber Usaha Sukses. Skripsi. Universitas Mercu Buana: Jakarta.

Elliott, K.S, (2002). “Precast Concrete Structures”. Oxford: Butterworth-Heinemann.

Husein, A. 2009. Manajemen Proyek. Yogyakarta: Andi Offset

Mulyono T. 2017. Perawatan Fasilits Pelabuhan. Jakarta: Universitas Negeri Jakarta.

Triatmodjo, B. 2009. Perencanaan Pelabuhan. Yogyakarta: Beta Offset.

H. Hasnidar, A. Ashury, Dan A. Yasir Baedah, “Tingkat Pemanfaatan Dermaga Terminal Peti Kemas: Studi Kasus Terminal Peti Kemas Pelabuhan Makassar”, Sensistek, Vol. 1, No. 1, Hlm. 104-106, Sep 2018.

N. Sarah, A. Ashury, Dan C. Paotonan, “Analisis Kinerja Operasional Peralatan Bongkar Muat Peti Kemas Di Pelabuhan Makassar”, Sensistek, Vol. 1, No. 1, Hlm. 100-103, Sep 2018.

M. F. B. Yusup, “Impact Analysis Of Implementation Of Bonded Warehouse Policy In Makassar Port New Port On Logistic Costs”, Journal of Maritime Technology and Society, vol. 1, no. 1, pp. 17-25, Feb. 2022.

Published

2022-11-26

How to Cite

Damayanti, R., & Ashury, A. (2022). CRITICAL PATH ANALYSIS OF LONG PRECAST CONCRETE WORKBEAM AT WHEAT WORK AT MAKASSAR NEW PORT USING THE PERT METHOD. SENSISTEK:Riset Sains Dan Teknologi Kelautan, 5(2), 175-179. https://doi.org/10.62012/sensistek.v5i2.24751

Issue

Section

Port Engineering and Management